Crystal River nuclear startup again delayed as costs approach $500 million

The reactor inside a 42-inch thick concrete container wall at the Crystal River nuclear power plant has been offline since September 2009.

Times (1996)

The reactor inside a 42-inch thick concrete container wall at the Crystal River nuclear power plant has been offline since September 2009.

Progress Energy has once again delayed restarting its Crystal River nuclear power plant north of Tampa Bay after discovering new cracks in the reactor building.

The good news is the company says the cracks are not a threat to public safety, despite the unfortunate timing of announcing the need for more repairs amid growing international concern over Japan's nuclear power plant crisis.

The bad news is Progress Energy has announced plans several times over the past 18 months to restart the Crystal River plant, located in Citrus County. But the company has been forced to postpone those startups due to concerns over the integrity of the 42-inch concrete wall surrounding the nuclear reactor. The price tag in extra costs due to the long delay is approaching half a billion dollars.

The facility, Progress Energy's sole nuclear power plant in Florida, was taken offline in September 2009 for refueling and maintenance. A crack or "delamination" discovered in the concrete wall surrounding the reactor was repaired. The plant was expected to begin operation next month once steel tension bands or "tendons" in the wall were carefully tightened to provide added strength to the containment building.

The containment building houses the plant's nuclear reactor, steam generators and other pumps and valves. (The electrical generators are in another building.) The structure is engineered to contain the rapid buildup of heat and pressure that would take place if a large pipe broke

Signs of new cracks were found as a result of that retensioning process. No new startup date has been set.

“There are indications of additional delamination (or separation) resulting from the repair work," Progress Energy stated Tuesday. "Engineers are evaluating the situation and will conduct a thorough assessment of repair options and the impact to the plant's restart plans."

"This has been a first-of-a-kind repair, and we will continue to move forward cautiously and deliberately," Progress Energy Florida CEO Vincent Dolan said in a statement.

The Crystal River nuclear plant began operating in 1977. Progress Energy wants to extend its operation another 20 years beyond 2016, the original lifespan of the plant's 40-year license.

Broken down, Progress Energy spent $150 million for repairs as of December and another $290 million to buy the electricity that otherwise would have been generated by the plant.

Part of those costs are covered by Progress Energy's insurance company, Nuclear Electric Insurance Limited. As of December, it had paid out $181 million to the utility. Of that, $117 million went toward buying replacement power and $64 million for repairs. Ongoing costs will raise the final price tag.

Progress continues to submit claims to its insurance company. The amount the insurance company doesn't pay will be passed on to its 1.6 million Florida customers.

Contact Robert Trigaux at trigaux@sptimes.com.

Crystal River nuclear startup again delayed as costs approach $500 million 03/15/11 [Last modified: Tuesday, March 15, 2011 10:47pm]
Photo reprints | Article reprints

© 2017 Tampa Bay Times

    

Join the discussion: Click to view comments, add yours

Loading...
  1. Report slams Pinellas construction licensing agency

    Local Government

    LARGO — The Pinellas County Construction Licensing Board mismanaged its finances, lacked accountability and violated its own rules, according to a scathing report released Wednesday by the county's inspector general.

    Rodney Fischer, the executive director of the Pinellas County Construction Licensing Board, resigned in January.  [SCOTT KEELER   |   Times]
  2. A meatless burger that tastes like meat? Ciccio Restaurants will serve the Impossible Burger.

    Food & Dining

    TAMPA — The most red-hot hamburger in the nation right now contains no meat.

    Luis Flores, executive chef at Ciccio Restaurant Group, prepares an Impossible Burger at Epicurean Hotel's Food Theatre. Impossible Burger is a plant-based burger that will launch on Sept. 27, 2017 in all the Ciccio Restaurant Group locations, except for Fresh Kitchen. "This burger caters to the carnivorous, not just the vegetarians" said Jeff Gigante, co-founder at Ciccio Restaurant Group. ALESSANDRA DA PRA  |   Times
  3. Construction starts on USF medical school, the first piece of Tampa's Water Street project

    Health

    TAMPA — Dozens of workers in hard hats and boots were busy at work at the corner of South Meridian Avenue and Channelside Drive Wednesday morning, signaling the start of construction on the University of South Florida's new Morsani College of Medicine and Heart Institute.

    Construction is underway for the new Morsani College of Medicine and USF Health Heart Institute in downtown Tampa. This view is from atop Amalie Arena, where local officials gathered Wednesday to celebrate the first piece of what will be the new Water Street District. The USF building is expected to open in late 2019. [ALESSANDRA DA PRA  |   Times]
  4. Tampa Bay among top 25 metro areas with fastest growing economies

    Economic Development

    Tampa Bay had the 24th fastest growing economy among 382 metro areas in the country for 2016. According to an analysis by the U.S. Bureau of Economic Analysis, Tampa Bay's gross domestic product, or GDP, increased 4.2 percent from 2015 to 2016 to hit $126.2 billion.

    Tampa Bay had the 24th fastest growing economy in the country for 2016. Rentals were one of the areas that contributed to Tampa Bay's GDP growth. Pictured is attorney David Eaton in front of his rental home. 
[SCOTT KEELER | Times]
  5. Tampa Bay cools down to more moderate home price increases

    Real Estate

    The increase in home prices throughout much of the Tampa Bay area is definitely slowing from the torrid rate a year ago.

    This home close to Bayshore Boulevard in Tampa sold for $3.055 million in August, making it Hillsborough County's top sale of the month. [Courtesy of Bredt Cobitz]