Florida Senate passes rewrite of nuclear advance fee

TALLAHASSEE — The Florida Senate on Friday passed a bill that for the first time attempts to scale back the unpopular nuclear fee on customer utility bills by tightening oversight by the state's utility regulators.

SB 1472 imposes new restrictions on the "early cost recovery" law passed in 2006 that allows electric companies to impose pre-construction costs for nuclear projects without any guarantee that the projects will be built. The bill passed unanimously with no discussion and will be sent to the House, which will take up a similar bill next week, the final week of the 60-day legislative session.

"The significance of this is it creates a process that, for the first time, only allows rate recovery for the process of obtaining a license,'' said Sen. John Legg, R-Trinity, who along with Sens. Wilton Simpson, R-Trilby, Jack Latvala, R-Clearwater, and Jeff Brandes, R-St. Petersburg, are sponsors of the Senate bill.

The Senate bill prohibits Progress Energy and Florida Power & Light from collecting the nuclear fees after July 1 unless they have shown proof of their intent to pursue a license for a nuclear reactor from federal authorities. The PSC has the power to determine how to interpret intent.

Once a company acquires a license, the bill triggers a review by the Public Service Commission to determine if it is moving the project forward. It also requires the company to justify the entire project instead of just the expenses. If regulators determine that the company is serious about its intentions to pursue a permit for a nuclear reactor, the bill reduces the interest rate on their capital costs, potentially saving customers $800 million over the 20-year life of the project.

"It still will allow nuclear projects to move forward but only based on the license,'' Legg said.

Since 2006, Progress Energy has charged customers more than $1 billion to expand the now-crippled Crystal River nuclear power plant and to start developing a new nuclear power plant in Levy County. The company terminated the Crystal River project but has kept $150 million of the money in profits from all its projects.

Florida Power & Light collected $530 million from the nuclear fee and used the money to finance expansions to its existing power plants at Turkey Point and in St. Lucie County. It has also proposed building two new reactors at Turkey Point but has not obtained a permit to do it.

Voter discontent with Progress Energy's troubled power plant has prompted four Tampa Bay area senators to take the more aggressive approach to revamping the law, although they have stopped short of repealing it.

"The Florida Senate has recognized the flawed policy that charges consumers in advance for risky and expensive new nuclear reactors," stated Susan Glickman, a consultant for Southern Alliance for Clean Energy which has urged lawmakers to repeal the 2006 law because it shifts the financial risk of building new nuclear reactors from companies to its customers.

"The bill which passed the Senate today offers more procedural protections for consumers although the devil is in the details,'' Glickman said. "Its impact is highly dependent on a rigorous review by the Florida Public Service Commission."

Progress Energy and FPL have repeatedly said they oppose the legislation but they have not forcefully lobbied against it.

Stephen Smith, executive director of Southern Alliance for Clean Energy, expressed skepticism that the PSC, whose members are chosen by a legislatively-controlled commission, would be aggressive consumer advocates.

"Our biggest concern though, is that the Florida Public Service Commission continues to fail consumers,'' Smith said. "The only way this bill actually works is if the Public Service Commission works."

Florida Senate passes rewrite of nuclear advance fee 04/26/13 [Last modified: Friday, April 26, 2013 6:53pm]
Photo reprints | Article reprints

© 2017 Tampa Bay Times

    

Join the discussion: Click to view comments, add yours

Loading...
  1. Massachusetts firm buys Tampa's Element apartment tower

    Real Estate

    TAMPA — Downtown Tampa's Element apartment tower sold this week to a Massachusetts-based real estate investment company that plans to upgrade the skyscraper's amenities and operate it long-term as a rental community.

    The Element apartment high-rise at 808 N Franklin St. in downtown Tampa has been sold to a Northland Investment Corp., a Massachusetts-based real estate investment company. JIM DAMASKE  |  Times
  2. New York town approves Legoland proposal

    News

    GOSHEN, N.Y. — New York is one step closer to a Lego dreamland. Goshen, a small town about fifty miles northwest of the Big Apple, has approved the site plan for a $500 million Legoland amusement park.

    A small New York town, Goshen approved the site plan for a $500 million Legoland amusement park. Legoland Florida is in Winter Haven. [Times file  photo]
  3. Jordan Park to get $20 million makeover and new senior housing

    Real Estate

    By WAVENEY ANN MOORE

    Times Staff Writer

    ST. PETERSBURG —The St. Petersburg Housing Authority, which bought back the troubled Jordan Park public housing complex this year, plans to spend about $20 million to improve the 237-unit property and construct a new three-story building for …

    Jordan Park, the historic public housing complex, is back in the hands of the St. Petersburg Housing Authority. The agency is working to improve the 237-unit complex. But the latest plan to build a new three-story building for seniors will mean 31 families have to find new homes. [LARA CERRI   |   Tampa Bay Times]
  4. Coming soon at two Tampa Bay area hospitals: a cancer treatment that could replace chemo

    Health

    A new cancer treatment that could eventually replace chemotherapy and bone marrow transplants — along with their debilitating side effects — soon will be offered at two of Tampa Bay's top-tier hospitals.

    Dr. Frederick Locke at Moffitt Cancer Center in Tampa is a principal investigator for an experimental therapy that retrains white blood cells in the body's immune system to fight cancer cells. The U.S. Food and Drug Administration approved these so-called "CAR-T" treatments for adults this month. In trials, 82 percent of cases responded well to the treatment, and 44 percent are still in remission at least eight months later, Locke said. [CHRIS URSO   |   Times]
  5. Regulator blasts Wells Fargo for deceptive auto insurance program

    Banking

    Wells Fargo engaged in unfair and deceptive practices, failed to properly manage risks and hasn't set aside enough money to pay back the customers it harmed, according to a confidential report by federal regulators.

    Wells Fargo engaged in unfair and deceptive practices, failed to properly manage risks and hasn't set aside enough money to pay back the customers it harmed, according to a confidential report by federal regulators.
[Photo by Spencer Platt/Getty Images, 2017]