Tuesday, April 24, 2018
Transportation

Bryan Dairy work is a temporary fix

They did some sort of repair on Bryan Dairy Road after it was paved east of the railroad tracks almost in front of TD Bank. The patched area appears like it was done by some amateur. Driving over it feels like they didn't put enough asphalt on and it is lower and rougher than the rest of the road. What a way to ruin a nice new road. Is there a way to correct this problem?

Jerry Klos

Unfortunately, after a multiyear project to improve Bryan Dairy Road, a water line break occurred just after construction was completed.

The Doc checked in with the county's public works folks to inquire about what's happening in this location and learned that the current rough patch is a temporary repair.

"Similar to the leak repair we made on McMullen-Booth Road this past spring/summer, the patch repair for the waterline leak on this arterial road is only temporary. Waiting a period of time will enable any settlement in the base material that might occur to occur," said county engineering supervisor Joe DeMoss. The temporary patch is being watched and once engineers are certain that conditions are stable, the stretch of road will be milled and a larger permanent patch will be applied. Workers will finalize the asphalt repair in coordination with upcoming paving work to the west at the intersection of Bryan Dairy/Starkey Road.

Doc, can you please help shed some light on the stalled bridge work that was being done near Mastry's Bait & Tackle at 17th Avenue S and Fourth Street? Construction was completed on the west side of the bridge but there appears to be no work being done on the east side of the roadway. The only traffic allowed now is southbound through the one narrow lane and northbound is still forced east on 18th Avenue S. There seems to be no end in sight in this fiasco of a construction job. I'm wondering if they even have a prospective date for completion.

Laroyh Harris

We checked in with Thomas Gibson, St. Petersburg's director of engineering, who acknowledged that the project is indeed a few months behind schedule.

The contractor doing the work completed the west half of Fourth Street S at Salt Creek bridge this past January, then began demolition of the east half of the bridge. The next phase of work required relocation of the overhead power lines along the east side of Fourth Street, which is necessary to allow vertical and horizontal clearance for the crane to work on the east side of the bridge.

Delay on the part of Progress Energy in getting the power lines relocated has set the project back, according to Gibson. The work was completed last week.

"The Progress Energy crew scheduling is beyond our control, and often affected by other priorities related to maintenance of their system and crew availability. Bridge construction has now resumed, and the current plan is to complete the east half of the bridge by June 15," Gibson wrote in an email last week.

Email Dr. Delay at [email protected] or follow @AskDrDelay on Twitter.

Comments
Free rides on PSTA and HART buses to celebrate Earth Day

Free rides on PSTA and HART buses to celebrate Earth Day

Those who use mass transit across the Tampa Bay area can ride for free on Sunday.To celebrate Earth Day, both the Pinellas Suncoast Transit Authority (PSTA) and the Hillsborough Area Regional Transit Authority (HART) will be offering free rides on Su...
Published: 04/19/18
She calmly landed the Southwest flight and broke barriers as a fighter pilot

She calmly landed the Southwest flight and broke barriers as a fighter pilot

The pilot’s voice was calm yet focused as her plane descended with 149 people on board."Southwest 1380, we’re single engine," Tammie Jo Shults, a former fighter pilot with the U.S. Navy, said. "We have part of the aircraft missing so we’re going to n...
Published: 04/18/18
Carlton: Thanks, Gov. Scott, for the dreaded trip across Interstate 4

Carlton: Thanks, Gov. Scott, for the dreaded trip across Interstate 4

The other day I had to go to Orlando from Tampa on Interstate 4, which has to be one of the most disliked highways in Florida. And I say this as someone who learned to drive on Miami’s I-95.It turned out to be the same root canal of a trip we’ve come...
Published: 04/18/18
NTSB: Blown Southwest jet engine showed ‘metal fatigue’

NTSB: Blown Southwest jet engine showed ‘metal fatigue’

PHILADELPHIA — A preliminary examination of the blown jet engine of the Southwest Airlines plane that set off a terrifying chain of events and left a businesswoman hanging half outside a shattered window showed evidence of "metal fatigue," according ...
Published: 04/18/18
Group promoting road safety out in force on 56th Street Monday

Group promoting road safety out in force on 56th Street Monday

TEMPLE TERRACE — If all goes as planned on Monday (April 23), at least 100 people will line the sides of one of the most dangerous stretches in Hillsborough County — 56th Street between Sligh Avenue and Busch Boulevard — in an effort to get motorists...
Published: 04/17/18
Updated: 04/18/18
Big dig’s big cost: Pasco tunnel idea carries $550 million price tag

Big dig’s big cost: Pasco tunnel idea carries $550 million price tag

NEW PORT RICHEY — Construction costs to tunnel under U.S. 41 in central Pasco could top a half-billion dollars, four times the projected price of building elevated lanes above the highway’s intersection with State Road 54.The cost estimate, said Comm...
Published: 04/17/18
Dr. Delay: How to find out if you qualify for a speed hump; updates on the Pinellas Bayway

Dr. Delay: How to find out if you qualify for a speed hump; updates on the Pinellas Bayway

I live in St. Pete and would like to know how I could go about getting a speed hump installed on my street. Where do I start?Manuel Reyes, St. PetersburgThe place to start would be by contacting the St. Petersburg Neighborhood Transportation Manager,...
Published: 04/16/18
Updated: 04/17/18
He got fed up with Miami traffic, so now he commutes with dolphins and pelicans

He got fed up with Miami traffic, so now he commutes with dolphins and pelicans

Parker Lake got sick of the rat race. Sick of working in a cubicle. Sick of commuting on Miami’s mean streets. Sick of being overweight from sitting at a desk or in traffic jams.So Lake quit his unfulfilling job, sold his car and moved to a house on ...
Updated one month ago
A sixth person killed by the high-speed Brightline train in Florida

A sixth person killed by the high-speed Brightline train in Florida

The Brightline train fatally struck a man Sunday, bringing the total killed by the train to six people since it began test runs last year.The Delray Beach Police Department announced on Twitter that a pedestrian was hit Sunday by a northbound Brightl...
Updated one month ago
Dr. Delay: Will the lights at 87th Avenue N and Fourth Street cause extra congestion?

Dr. Delay: Will the lights at 87th Avenue N and Fourth Street cause extra congestion?

Massive new street signals were erected at the intersection of 87th Avenue N. and Fourth Street, just four blocks north from the light-controlled intersection at 83rd Avenue N. At the same time a new WaWa store/gas station is being constructed near 8...
Updated one month ago