Monday, November 20, 2017
Transportation

Bryan Dairy work is a temporary fix

RECOMMENDED READING


They did some sort of repair on Bryan Dairy Road after it was paved east of the railroad tracks almost in front of TD Bank. The patched area appears like it was done by some amateur. Driving over it feels like they didn't put enough asphalt on and it is lower and rougher than the rest of the road. What a way to ruin a nice new road. Is there a way to correct this problem?

Jerry Klos

Unfortunately, after a multiyear project to improve Bryan Dairy Road, a water line break occurred just after construction was completed.

The Doc checked in with the county's public works folks to inquire about what's happening in this location and learned that the current rough patch is a temporary repair.

"Similar to the leak repair we made on McMullen-Booth Road this past spring/summer, the patch repair for the waterline leak on this arterial road is only temporary. Waiting a period of time will enable any settlement in the base material that might occur to occur," said county engineering supervisor Joe DeMoss. The temporary patch is being watched and once engineers are certain that conditions are stable, the stretch of road will be milled and a larger permanent patch will be applied. Workers will finalize the asphalt repair in coordination with upcoming paving work to the west at the intersection of Bryan Dairy/Starkey Road.

Doc, can you please help shed some light on the stalled bridge work that was being done near Mastry's Bait & Tackle at 17th Avenue S and Fourth Street? Construction was completed on the west side of the bridge but there appears to be no work being done on the east side of the roadway. The only traffic allowed now is southbound through the one narrow lane and northbound is still forced east on 18th Avenue S. There seems to be no end in sight in this fiasco of a construction job. I'm wondering if they even have a prospective date for completion.

Laroyh Harris

We checked in with Thomas Gibson, St. Petersburg's director of engineering, who acknowledged that the project is indeed a few months behind schedule.

The contractor doing the work completed the west half of Fourth Street S at Salt Creek bridge this past January, then began demolition of the east half of the bridge. The next phase of work required relocation of the overhead power lines along the east side of Fourth Street, which is necessary to allow vertical and horizontal clearance for the crane to work on the east side of the bridge.

Delay on the part of Progress Energy in getting the power lines relocated has set the project back, according to Gibson. The work was completed last week.

"The Progress Energy crew scheduling is beyond our control, and often affected by other priorities related to maintenance of their system and crew availability. Bridge construction has now resumed, and the current plan is to complete the east half of the bridge by June 15," Gibson wrote in an email last week.

Email Dr. Delay at [email protected] or follow @AskDrDelay on Twitter.

Comments
Mother reconciles with Plant City DMV employee who made her stand outside with baby

Mother reconciles with Plant City DMV employee who made her stand outside with baby

PLANT CITY — After Liz Gately was told to wait outside the Plant City’s Tax Collector office to renew her car registration with her 1-year-old last week, the internet fought back. Facebook posts from Gately, 27, as well as bystanders and other mother...
Published: 11/16/17
Holiday events begin, annual traffic snarls follow

Holiday events begin, annual traffic snarls follow

A few favorite holiday events are gearing up and that means impact to traffic, starting with the annual Times Turkey Trot, which will temporarily close streets Thanksgiving morning in Clearwater beginning at 6 a.m. until approximately noon. The follo...
Published: 11/15/17
Moms with infants told to wait outside Plant City DMV

Moms with infants told to wait outside Plant City DMV

PLANT CITY — Liz Gatley needed to renew her car registration. As if that task wasn’t cumbersome enough, she says a Department of Motor Vehicles manager told her she had to wait outside until she could be served because her 1-year-old daughter was wit...
Published: 11/10/17
Updated: 11/11/17
The Cross Bay Ferry won’t come back this fall. What about 2018?

The Cross Bay Ferry won’t come back this fall. What about 2018?

Still waiting for the Cross Bay Ferry to return? It’s going to be a while — say, 2018 at the earliest.The ferry’s supporters, most notably St. Petersburg Mayor Rick Kriseman, had hoped to bring the boat back for another season after the first six-mon...
Published: 11/10/17

Work on Sunshine Skyway’s rest areas to last two more years

We often go fishing near the Sunshine Skyway Bridge and are wondering what’s happening with the rest area and parking lot? It looks like there’s work going on there. How long will the rest area be closed off?Mike WalkerThis is a state Department of T...
Published: 11/09/17
Updated: 11/13/17
Hillsborough loses transit leader Katharine Eagan to a better funded agency

Hillsborough loses transit leader Katharine Eagan to a better funded agency

TAMPA — Katharine Eagan, the leader of Hillsborough County’s transit agency, is leaving the job just a month after implementing a widespread overhaul of the county’s bus network.She will take over as CEO of the Port Authority of Allegheny, Pa., which...
Published: 11/08/17
Updated: 11/09/17
Speakers give mixed reviews to new Hillsborough bus-route overhaul

Speakers give mixed reviews to new Hillsborough bus-route overhaul

TAMPA — Hillsborough’s transit agency heard its first public comment Monday since overhauling its bus network and cutting about 20 percent of its routes last month.A handful of people spoke at the agency’s board meeting, with one praising the new net...
Published: 11/06/17
Updated: 11/07/17
New DOT work plan includes $32 million for U.S. 41/SR 54 interchange

New DOT work plan includes $32 million for U.S. 41/SR 54 interchange

LAND O’LAKES — Twenty-one months ago, the Florida Department of Transportation said it was hitting the brakes on planning improvements at a traffic-clogged intersection in central Pasco.Instead, the DOT said it would await recommendations from Pasco ...
Updated one month ago
Planning commission to rethink Bloomingdale Avenue reversible lane proposal

Planning commission to rethink Bloomingdale Avenue reversible lane proposal

RIVERVIEW — Business owners and residents of Bloomingdale Avenue breathed a cautious sigh of relief Monday after Hillsborough County planning commissioners said converting the busy roadway into reversible lanes is no longer an option.The proposed cha...
Updated one month ago
From Nature’s Way to ‘raceway:’ residents worry about speeding on neighborhood boulevard

From Nature’s Way to ‘raceway:’ residents worry about speeding on neighborhood boulevard

VALRICO — It’s a sound that many residents living along Nature’s Way Boulevard say is all too familiar.Engines revving and then the sound of motorcycles and cars flooring the gas pedal on a 30-mile-per-hour roadway often wake up residents in the midd...
Updated one month ago