Make us your home page
Instagram

Today’s top headlines delivered to you daily.

(View our Privacy Policy)

The latest rundown on the new Pinellas Bayway bridge

The new Pinellas Bayway bridge, which will be higher and include four lanes, should be completed by the end of 2014 or early 2015.

SCOTT KEELER | Times

The new Pinellas Bayway bridge, which will be higher and include four lanes, should be completed by the end of 2014 or early 2015.

Lots of questions have been pouring into the Doc's mailbox about the ongoing Pinellas Bayway bridge replacement project. The nearly 50-year-old, two-lane drawbridge will be replaced with a higher four-lane bridge, and work has been in progress for a few months. Here's a rundown of the most frequently asked questions and the inside skinny we got from Kris Carson of the state Department of Transportation:

How do the new bridge pilings get driven into the sand?

The pilings are driven using a diesel pile-driving hammer. Depending on the height that the hammer drops on a given setting, it transfers a large amount of energy into the pile to force it into the ground.

Is there bedrock under the sand and water that those pilings go into?

There is no bedrock in the area. The pilings are driven down to a hard sand layer or to a deeper hard clay layer to achieve the required strength to support the bridge.

What about the motion of the water? How do the pilings not tip over?

The design plans include a minimum depth that the pilings must be driven in order to make sure the bridge supports are not affected by the current and wave action (referred to as "scouring''). The design calculates the anticipated worst scour that would occur during a 100-year storm event and the minimum depth is much deeper than that worst-case scenario. So say we are hit by a storm on the scale of the epic 1921 hurricane that pummeled Pinellas County with 100-mile winds. The new bridge should still be standing.

How far down under the surface do they go?

Depending on the location, the piles are driven into the ground to depths varying between 75 to 115 feet below the water elevation. Once all of the pilings are driven for each pier location, they are cut off at the required top elevation and a reinforced concrete footing is built on top of the 16 piles. Each footing measures is 22 feet by 22 feet and 6 feet deep. The columns and pier caps on top of each footing are being constructed to eventually support the new concrete beams and concrete bridge surface.

Speaking of concrete, how much is in one of the 16 piers?

Many components come together to make up one of the support piers for the new bridge. First, there are 16 pilings for each separate column being constructed on the project (two columns per pier). Once a piling is driven to the specified depths, a steel-reinforced concrete footer is constructed on top of the piling. The footers contain approximately 100 cubic yards of concrete. On top of the footers are the columns and pier cap. Since these vary in height between 17 to 65 feet for the new bridge, the overall concrete varies between 110 cubic yards to 230 cubic yards. So, for each pier in the water, the overall concrete quantities vary between 210 and 330 cubic yards.

In total, more than 23,500 cubic yards of concrete and 2,300 tons of reinforcing steel will be placed on site to build the new bridge. This total doesn't include the concrete and steel used to construct the pre-cast pilings and beams. To put that in perspective, we're talking about enough concrete to fill 280 residential swimming pools.

How much asphalt will be used?

Nearly 6,700 tons will be used to build the new lanes and resurface the existing travel lanes.

What about landscaping?

More than 100 palm trees and other landscaping will be planted along the bridge and its new wider approaches.

How many people are working on the project?

Approximately 60 people are working on the project on a given day, including the prime contractor, Orion Marine, and various sub-contractors and DOT staff.

How much does the whole thing cost?

Orion Marine Group was awarded a $40 million contract.

When will the new bridge be done?

The completion date is sometime near the end of 2014 or early 2015, depending on weather and other factors.

Email question to docdelay@gmail.com and follow Dr. Delay on Twitter @AskDrDelay.

The latest rundown on the new Pinellas Bayway bridge 08/04/12 [Last modified: Saturday, August 4, 2012 4:30am]
Photo reprints | Article reprints

© 2017 Tampa Bay Times

    

Join the discussion: Click to view comments, add yours

Loading...
  1. Ole Miss football coach Hugh Freeze resigns over "inappropriate conduct"

    College

    OXFORD, Miss. — Mississippi coach Hugh Freeze was at Jackson Country Club on Wednesday night, giving his yearly rah-rah speech about the Rebels' overcoming adversity and getting ready for the college football season.

    If Hugh Freeze hadn’t resigned, Ole Miss says it would have fired him for violating his contract’s moral turpitude clause.
  2. Fennelly: With playoff chase in high gear, it's time for Rays to make a move

    The Heater

    ST. PETERSBURG

    Thursday was an off-day for the Rays, who are coming off a solid western swing. I assume there was no rest for the tag-team Rays baseball brain trust of Matt Silverman, Erik Neander and Chaim Bloom, whose job it is to improve this team in advance of the trade deadline. They've done a good job …

    Evan Longoria is glad to see the Rangers coming to town: He’s batting .296 against them with 15 homers and 56 RBIs in 69 career games.
  3. World's plastic waste could bury Manhattan 2 miles deep

    Environment

    WASHINGTON — Industry has made more than 9.1 billion tons of plastic since 1950 and there's enough left over to bury Manhattan under more than 2 miles of trash, according to a new cradle-to-grave global study.

    Plastic trash is compacted into bales ready for further processing at the waste processing dump on the outskirts of Minsk, Belarus.
  4. Sen. John McCain's type of cancer did not slow Tampa woman

    Health

    TAMPA — When 35-year-old Beth Caldwell heard about Sen. John McCain's brain tumor this week, she hoped he would stay positive.

    That's what helped her, she said.

    Throughout her battle with brain cancer, Beth Caldwell, 35, keeps her sons Gavin, 10, and Triston, 7, on her mind.
  5. A week later, the lengthy, costly rebuilding plan for the Pasco sinkhole begins

    Public Safety

    LAND O'LAKES — A week after a massive sinkhole opened in Pasco County, county officials have begun planning the long-term cleanup, which could take months and millions of dollars.

    A sinkhole in Land O'Lakes, Fla., is seen Wednesday, July 19, 2017. The sinkhole ?‘ already one of the largest in Pasco County in decades ?‘ measures about 235 feet in width and 50 feet in depth, with the potential to expand further.