When will the Rays build their new stadium? A construction timeline.

Starting next year, construction will take about 20 years to build out the 86-acre Historic Gas Plant District.
 
This animation shows the three phases of development expected for the Rays and Hines' redevelopment of St. Petersburg's 86-acre Tropicana Field site. First, between 2024 and 2029, a new stadium and other buildings will go up east of Tropicana Field. After Tropicana Field is demolished, from 2030 to 2035, new office, residential and retail buildings will go up on the land where it once stood. Finally, from 2036 to 2043, developers will build out the southwest corner of the site with additional office, retail and residential space.
This animation shows the three phases of development expected for the Rays and Hines' redevelopment of St. Petersburg's 86-acre Tropicana Field site. First, between 2024 and 2029, a new stadium and other buildings will go up east of Tropicana Field. After Tropicana Field is demolished, from 2030 to 2035, new office, residential and retail buildings will go up on the land where it once stood. Finally, from 2036 to 2043, developers will build out the southwest corner of the site with additional office, retail and residential space. [ Tampa Bay Rays / Hines ]
Published Sept. 20|Updated Sept. 22

This much we know: The Rays are slated to play their last game at Tropicana Field in 2027. They’ll move into their just-announced $1.3 billion stadium next door in 2028.

But what about the rest of the 86-acre Historic Gas Plant District? When will construction begin, and how long will it last?

The city of St. Petersburg and Pinellas County always knew this would be a long-term project, as did the Rays and their development partner, global real estate investment and development firm Hines. Of the four proposals submitted to the city, theirs had the longest timeline, wrapping up in 2043 — a good four years longer than the next-longest timeline.

Related: Check out renderings of the Rays' new stadium in St. Petersburg

Here’s how the next 20 years of this $6.5 billion project should unfold.

A rendering of the Rays' news stadium and development project for the Historic Gas Plant District. Courtesy of Hines
A rendering of the Rays' news stadium and development project for the Historic Gas Plant District. Courtesy of Hines [ Courtesy of Hines ]

2023 to 2026

Before anything can happen, the city and county must close deals with Hines and the Rays. City Administrator Rob Gerdes and County Administrator Barry Burton said they expect to present term sheets to the City Council and County Commission in October, with final agreements and votes early next year. If all goes as planned, the team and Hines plan to break ground around this time next year.

The first order of business: Parking. The new stadium will go in what is now Tropicana Field’s parking lot, which means the team needs someplace for fans to park in 2025, 2026 and 2027. Starting next year, construction will begin on three parking garages with more than 3,300 spaces.

“It’s really like a giant jigsaw puzzle,” said Hines senior managing partner Michael Harrison. “We’re building new parking facilities that will be dedicated to the ballpark and available for public use when it’s not in play for baseball, and that’ll free up the area that we need to begin construction on the ballpark, as well as Phase 1 of development, which will be surrounding and adjacent to the ballpark.”

That Phase 1, according to the original Rays-Hines proposal — which may be adjusted during negotiations — is split into two sub-phases. During the first, from 2024 to 2026, managers expect to begin all other aspects of the project, aiming to have “a critical mass of uses” open for business before the 2028 season.

Among the projects scheduled for construction during this period: An entertainment venue capable of seating up to 4,000; 50,000 square feet of cultural space including a new Woodson African American Museum of Florida; 400,000 square feet of office space; 80,000 square feet of retail space; and more than 800 residences and 300 hotel rooms. (The project’s total number of residences and hotel rooms has increased from the original proposal, so an exact phase-by-phase count is not available.)

Spend your days with Hayes

Spend your days with Hayes

Subscribe to our free Stephinitely newsletter

Columnist Stephanie Hayes will share thoughts, feelings and funny business with you every Monday.

You’re all signed up!

Want more of our free, weekly newsletters in your inbox? Let’s get started.

Explore all your options
This visualization, pulled from the Tampa Bay Rays and Hines' redevelopment proposal for St. Petersburg's 86-acre Tropicana Field site, shows how the site expects to evolve from 2024 to 2029, with the new stadium and other buildings in blue. Tropicana Field, in white, is slated for demolition in 2028.
This visualization, pulled from the Tampa Bay Rays and Hines' redevelopment proposal for St. Petersburg's 86-acre Tropicana Field site, shows how the site expects to evolve from 2024 to 2029, with the new stadium and other buildings in blue. Tropicana Field, in white, is slated for demolition in 2028. [ Tampa Bay Rays / Hines ]

2027 to 2029

As the Rays wind down their stay in Tropicana Field, developers will be putting the finishing touches on a new ballpark.

By the end of the 2027 season, according to the proposal, developers hope to have begun construction on more than 2,100 on-site multifamily homes. A number of those will be dedicated to affordable, workforce and senior housing. Also coming in 2027: a fourth new parking garage with an additional 770 spaces.

Once Tropicana Field is demolished in 2028, developers will reestablish the street grid west of Booker Creek, including east-west bridges across the creek itself. This process is expected to take 18 months.

In all, from 2027 to 2029, the development will add more homes and hotel rooms, plus 200,000 more square feet of office space and 70,000 square feet of retail. Most of that will go up east of Booker Creek, and north and east of the new stadium.

2030 to 2035

This visualization, pulled from the Tampa Bay Rays and Hines' redevelopment proposal for St. Petersburg's 86-acre Tropicana Field site, shows how the site expects to evolve from 2030 to 2035, with the newest buildings in blue, many sitting on land where Tropicana Field stands today.
This visualization, pulled from the Tampa Bay Rays and Hines' redevelopment proposal for St. Petersburg's 86-acre Tropicana Field site, shows how the site expects to evolve from 2030 to 2035, with the newest buildings in blue, many sitting on land where Tropicana Field stands today. [ Tampa Bay Rays / Hines ]

With ballpark development well in the past, the project will pivot to going vertical on the land where Tropicana Field once sat, starting closer to the western edge of Booker Creek. This far out, the numbers are malleable, but the proposal calls for another 1,900 residents, 175 hotel rooms, 600,000 square feet of office space and 100,000 square feet of retail space to go up during this time.

2036 to 2043

This visualization, pulled from the Tampa Bay Rays and Hines' redevelopment proposal for St. Petersburg's 86-acre Tropicana Field site, shows the final phase of expected development, with the buildings in blue at the southwest corner of the site today.
This visualization, pulled from the Tampa Bay Rays and Hines' redevelopment proposal for St. Petersburg's 86-acre Tropicana Field site, shows the final phase of expected development, with the buildings in blue at the southwest corner of the site today. [ Tampa Bay Rays / Hines ]

Thirteen years from now, development will focus on the southwest corner of the site, farthest from the new stadium, as developers finish out what’s left. By the end, the plan is to have 6,000 residential units on- and off-site, including at least 1,200 dedicated to affordable and workforce housing, 1.4 million square feet of office space, 750,000 square feet of retail, 750 hotel rooms and 100,000 square feet of convention space.

The goal is to have everything wrapped up in 2043 — at about the time the Rays’ new ballpark turns 15.